Store House Construction

by Trai Davenport on August 15, 2011 · 0 comments

in Construction

June 2012

  1. We finished up the water lines to the Church, and our water was turned on this week. Glory to God!

May 2012

  1. We finished the installation of our HVAC. We installed a 4 ton Heat pump that should have plenty of capacity to keep the Church Building cool in the summer and warm in the winter. This is a big milestone for us in the construction process.

Dec. 15 2011

As of this week we have checked off quite a few things from our to do list.  We have completed the following:

  1.  Trimming out all the windows inside and outside.
  2. Installing all our interior doors, because one of the doors leads to the garage area which is not insulated.
  3. Having the ceiling insulation blown in.
  4. Preparing the area for the HVAC install.
  5. Finishing the electrical wiring and running our permanent power.

We have also accomplished a few other things.

  1. Installed most of the ceiling trim in the main part of the building and around the stage/pulpit.  (We needed to install trim to stop the draft/weatherproof the ceiling drywall.)


Fall 2011

Starting this Fall we set a goal to have our Storehouse weathertight for the winter.  That consists of:

  1.  Trimming out all the windows inside and outside.
  2. Installing all our interior doors, because one of the doors leads to the garage area which is not insulated.
  3. Having the ceiling insulation blown in.
  4. Preparing the area for the HVAC install.
  5. Finishing the electrical wiring and running our permanent power.
  6. Installing the HVAC system.
  7. Waterproofing the exterior.

Leave a Comment